Rapid bottom-line improvement
Contact our Team
Next Steps...
Homepage > Successes > Triumph Business Systems

TOC Case Study: Triumph Business Systems

Before

  • Turnover £14 million
    inventory £1,800,000
    4 week lead times
    due date performance 75 percent

After

  • Turnover £23 million
    inventory £750,000
    lead times reduced to less than 7 days, and in some cases to 72 hours
    due date performance greater than 95 percent – increased by 20 percent
    prices for an average trailer load of manufactured goods (the only effective measure of work) fell 30 percent
Goldratt UK - Return HomeGoldratt UK - Leading Provider of Results Based Projects in the UK
Tel: +44 (0) 1234 834510 - Email info@goldratt.co.uk
©2007 Goldratt UK