TOC Case Study: Ford Motor Company

Electronic Division Experience

LEAD TIME
(from release of material until shipping)
AVERAGE ON ALL SITES FOR ALL PRODUCTS
  • Before improvement project: 10.6 days
  • After two years of implementing JIT: 8.5 days
  • After one year of implementing TOC: 2.2 days
  • Currently: Less than two shifts
More reported results:
  • Customer satisfaction improved >75%
  • Able to move to real time SPC on the floor
  • Responsiveness and learning 300% faster
  • 20% more floor space allowing introduction of new products
  • Material handling and tracking reduced 50%
  • Facilities investment reduced 25%
  • Suggestions process went from 150 days to 10 days
  • Scheduling process went from 16 days to 5 days to 1 day